Leesburg’s downtown Main Street Streetscape Project is near completion and Main Street will be open in time for Bikefest beginning on April p:BC BCJ Body Copy RR drop cap 24, City Manager Al Minner said Tuesday.p:BC BCJ Body Copy RR drop cap
“It is probably 85 to 90 percent complete,” Minner said. “We are pretty much on schedule. We are finishing up the asphalt and are finishing pouring concrete at the intersection of U.S. (Highway) 27 and Main Street. We have most of the landscaping in.”
Landscaping and work on the archways still needs to be completed, Minner said.
City officials are ensuring the street’s new pavement will be protected when Bikefest opens, he added.